Monday, July 12, 2010
Interior Update
With the installation of the rigid foam on the roof area we have been able to comfortably work on the interior detailing while it is raining outside. We have been getting everything prepped and ready for the concrete floor to be poured. The plumbing, HVAC and mechanical contractors have been stubbing up everything so the concrete will get poured to it. We have been placing 1x6 around the walls for the concrete to be poured. The exterior walls have a line of sealant caulk applied to the sub-floor and bottom plate before the 1x6 to make an airtight seal to the out doors. We used 1x6 so there would still be exposed wood for the drywall to sit on so it will not suck up water from the concrete. We should be getting the floor started in the next week or so. Stay tuned the next thing on the agenda will be finishing the cold roof sandwich.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment